The Virginia Department of Transportation will build a shared-use path on Old Meadow Road and a pedestrian/bicycle bridge over I-495 (via VDOT)

The Virginia Department of Transportation has selected Shirley Contracting Company to build a bridge and shared-use path along Old Meadow Road, providing a crucial connection from Tysons Corner Center to the McLean Metro station over I-495.

The contract was awarded in June but has not been finalized yet. VDOT project manager Abraham Lerner confirmed that construction is still expected to start this summer.

“At this time we do not have a specific date when the construction of the Tysons Old-Meadow Road project is expected to begin,” Lerner told Tysons Reporter by email. “We need to finalize the administrative processes related to getting the contractor under contract…We will reach out to the community prior to starting construction work.”

Based in Lorton, Shirley Contracting is an affiliate of Clark Construction, which has been involved in numerous other projects in Fairfax County, including the second phase of Metro’s Silver Line project.

The project will provide a bridge over the Capital Beltway for pedestrians and bicyclists, who currently have no easy way to cross the interstate at the Route 123 interchange. It will also involve the addition of a 4,662-foot-long, 10-foot-wide trail along the west side of Old Meadow Road.

Construction will unfold in two phases due to the availability of funding, according to Lerner.

The first phase will introduce the bridge and a portion of the shared-use path up to the Provincial Drive intersection. Construction will be supported by $8.5 million in funding and is expected to be complete in the summer of 2022.

The shared-use path will then be extended to Route 123 during the project’s second phase, which will begin construction once “additional funding becomes available,” VDOT says.

0 Comments

More Capital Bikeshare stations are in the works for the Tysons area, specifically in Merrifield and Vienna.

The Fairfax County Department of Transportation has proposed adding 10 new stations in the following locations, including what would be the bike-sharing service’s first stand at the Vienna Metro station:

  • Caboose Commons
  • Circle Woods Drive and Lee Highway
  • Gatehouse Road and Telestar Court
  • Hartland Road and Harte Place
  • Inova Fairfax Medical Campus
  • Javier Road and Arlington Boulevard
  • Kingsbridge Drive and Beech Grove Drive
  • Mission Square Drive
  • Prosperity Flats
  • Vienna Metro South Entrance

The expansion would bring the Tysons area up to 29 Bikeshare stations, including 15 in Tysons and one at the West Falls Church Metro stop. Fairfax County also has 16 stations in Reston, which is getting its own expansion starting in July.

Fairfax County is eager to expand Bikeshare in Merrifield, because the three existing stations that were installed there in 2019 have proven successful, generating some of the most trips per site in the county prior to the COVID-19 pandemic, according to FCDOT spokesperson Robin Geiger.

Vienna has been considered a candidate for Bikeshare since at least 2018, when the county worked with the town, the City of Fairfax, and George Mason University on a feasibility study.

“Plans to expand to the Vienna Metrorail station are underway to provide connectivity to the surrounding community,” Geiger said by email. “The Vienna area stations will also help provide access to the City of Fairfax, who is working to bring CaBi to their part of the region as well.”

While it is not included in Fairfax County’s expansion, Town of Vienna spokesperson Karen Thayer says the Virginia Department of Transportation has granted the town’s request for funding to add Bikeshare stations at multiple locations, including the Town Green and community center.

The total project cost will be $272,400, which covers engineering and design, equipment, and installation.

“We are currently waiting for VDOT to complete its internal process and respond with an agreement,” Thayer said.

For the county project, Geiger says transportation officials looked at a variety of factors when selecting the proposed locations, including the density of development and the potential to generate a lot of trips. The need for bicycling infrastructure is also considered “in an effort to improve transportation equity,” she says.

“On a more granular level, we like to place stations in areas that are already paved — on-street parking lanes are often easy for [installation] and future servicing, and has only a small impact on available car parking,” Geiger wrote, adding that docks typically take up no more than one or two parking spots.

The Merrifield expansion will be primarily funded with a $497,100 I-66 Commuter Choice grant, though that won’t cover the full cost of the project, which Geiger says is currently estimated to be around $600,000.

While Bikeshare usage in the Tysons area consistently rose prior to the pandemic, COVID-19 sank both ridership and membership numbers systemwide as people limited travel and many started working from home.

“At its worst, early in the pandemic membership was around 20% of ridership when compared to past years,” Geiger said by email. “Most of the lost trips were by annual members who were commuting by bicycle.”

Fairfax County saw a 50% decrease in Bikeshare riders in 2020 overall compared to 2019.

Geiger says ridership levels started to pick back up last summer, primarily from non-members, meaning people who were utilizing the service for a single trip or day instead of getting an ongoing subscription.

“Usage patterns systemwide changed as well, with fewer trips to Metro stations, but more to recreational locations, and grocery stores,” she said.

0 Comments

Morning Notes

Fountains outside The Verse condos in The Boro (photo by John G. Colby)

Capital One Adopts Hybrid Work Model — The founder and CEO of Capital One, which employs almost 10,000 people in the D.C. area, told workers yesterday (Tuesday) that its U.S. offices, including its headquarters in Tysons, will reopen on Sept. 7. The company will shift to a hybrid model where employees can work virtually on Mondays and Fridays with no requirements for how many days they need to be in the office. [WTOP]

Traffic Calming Measures Coming to Vienna and McLean — The Fairfax County Board of Supervisors voted last Tuesday (June 22) to approve the installation of “$200 Additional Fine for Speeding” signs along Vaden Drive between I-66 and Lee Highway near the Vienna Metro station. The county will also spend $40,000 to install four speed humps on Churchill Road in McLean. [Sun Gazette/Inside NoVA]

Founders Row Apartments Start Preleasing — The 322-unit Modera apartment building and 72-unit Verso senior living complex in Falls Church City’s Founders Row development are now preleasing in anticipation of opening later this year. The site will also host a six-story, mixed-use building with ground-floor retail and a movie theater, and a second phase is currently in the works. [Mill Creek Residential/PR Newswire]

Falls Church Among Healthiest U.S. Communities — The City of Falls Church came in third in U.S. News & World Report’s fourth annual Healthiest Communities rankings, the same spot that it has occupied for the last two years. Fairfax County made the top 15 at No. 14. [Patch]

0 Comments

(Updated at 6 p.m.) Fairfax County’s first venture into self-driving public transportation has encountered impatient drivers and other difficulties, but the autonomous shuttle in Merrifield could still serve as a roadmap for expansion and future projects.

Operating between the Mosaic District and Dunn Loring-Merrifield Metro station since October, the high-tech Relay service navigates through bustling areas and amongst shoppers, giving free rides and demonstrating the possibilities offered by autonomous vehicles.

Eta Nahapetian, a manager with the Fairfax County Department of Economic Initiatives, remembers watching “Star Trek” as a kid, along with flying cars in the animated TV show “The Jetsons.”

“Here we are, trying to make some of those childhood cartoons a reality,” she said on June 10 during a webinar about autonomous technology, “Creating an Autonomous Vehicle Ecosystem in Virginia.”

Sarah Husain, a transportation planner with the Fairfax County Department of Transportation, said the technology has elicited high interest from the community for how it helps people with disabilities.

During the presentation, Husain also described some of the challenges that have emerged during the pilot project, which is a joint effort between the county and Dominion Energy.

She said drivers can get impatient and illegally pass it, so officials with the project worked on adding signage and enlisted the Fairfax County Police Department to help with the issue.

In response to complaints about vehicles passing the autonomous shuttle, the McLean District Station has assigned officers to conduct extra patrol and enforcement to address drivers “speeding or passing Relay,” the FCPD said.

“We’d like to ask for our community’s patience when driving behind the shuttle,” police said. “Relay should only be passed, with care, when a full lane is available.”

According to the county, “Do not pass” signage was installed alongside Eskridge Road and Merrilee Drive in March 2021. Stickers with the same message were also placed on the shuttle.

“We sought out these challenges with the pilot,” Husain said, noting several solutions that came forth, such as installing monitoring devices that detect if the shuttle needs more time to pass through an intersection.

The technology remains limited in some ways. For instance, if an idled vehicle, such as a parked car, is in the way, a shuttle attendant has to take over in manual mode to advance the shuttle.

The shuttle runs from 10 a.m. to 2 p.m. Monday through Thursday from the Dunn Loring station to the Barnes & Noble in the Mosaic District. It’s designed to fill the “first/last mile” need in public transportation, connecting travelers to their ultimate destinations.

Fairfax County is seeking additional funding to continue Relay’s length of service and expand the routes that it serves. The pilot project is slated to end in August.

Dominion Energy, which supplied the shuttle, says an expansion of the pilot is among many options that it is considering for future uses of automated vehicle technology.

“Dominion Energy is considering other opportunities that may include an expansion of the current project,” Dominion Innovation Strategist Julie Manzari said. “The purpose of the pilot is to learn and gather information that will help us adjust or pivot to other concepts.”

0 Comments
Map of the West Falls Church Metro development sites (photo courtesy EYA)

Concerns raised by both local citizens and Fairfax County Planning Commission members over the impact of a new West Falls Church Metro station development plan prompted the commission to defer a vote on the project on Wednesday (June 16).

The West Falls Church Metro station is one of the most underutilized stations in the Metro system, and the Washington Metropolitan Area Transit Authority has enlisted developer EYA to turn the site into a mixed-use development.

The plan was endorsed by a task force appointed by Dranesville District Supervisor John Foust, but at Wednesday’s public hearing, several nearby residents and civic association representatives spoke out with concerns about the project — though others praised it as an improvement over the existing space.

“There are several focused criticisms and concerns raised about the current proposal by the [McLean Citizens Association] and by some of the nearby residents, who feel that we need to go further than this plan suggests,” said Dranesville District Planning Commissioner John Ulfelder.

Much of the criticism focused around the effect of traffic brought by the project on nearby roads that the county acknowledges were not made to support a sizable increase in density.

Braddock District Commissioner Mary Cortina said she was concerned that the plans fail to adequately address pedestrian safety.

“The text I see in the pedestrian area talks about convenience and comfort: it doesn’t talk about safety,” Cortina said. “This is life and death. We have to call out safety where we have pedestrian sections because that should be a priority.”

County staff said a follow-up study will look at identifying funding for pedestrian safety and traffic improvements for nearby streets that are outside of the scope of the current project but will still likely be affected by it.

“Haycock Road and Route 7 prevent a lot of people from crossing safely [to the Metro],” said Tim Kutz, a transportation planner with the Fairfax County Department of Transportation. “That’s something we’re going to look at further in the transportation plan looking at the surrounding neighborhood. It’s important that people have an opportunity to bike and walk safely…A lot of older neighborhoods don’t have sidewalks, don’t have crosswalks, and don’t have connectivity.”

Kutz said the funding for those future pedestrian improvements is something the county would “have to explore” later.

Some nearby residents commented that they support the project, notably Cheryl Smith, who represented the Gates at West Falls Condominiums and served as the majority vote for the West Falls Church TSA Task Force.

Smith argued that the project would be a net increase in terms of quality of life for those surrounding the project, but others disagreed.

“The WMATA site is not suitable,” said Adrienne Whyte, representing the recently-launched Reclaim Fairfax County group. “This is a lovely but limited fiction.”

Whyte said the West Falls Church Metro station is intended to be a neighborhood-serving station rather than a site for significant developments.

In the middle was Phil Cooke from the McLean Citizens’ Association, who said the MCA supported the developer’s plans, but with the provision that the county must further study ways to address the potential consequences of increased density and congestion.

“[This] will strain Route 7 congestion further than it already is,” Cooke said. “Folks will seek to avoid Haycock and Route 7 and exit the back way, increasing local congestion.”

At Ulfelder’s suggestion, the board voted unanimously to defer its decision on the comprehensive plan amendment to the June 30 meeting, to collect further feedback and reflect on public comment before the Commission votes on the project.

0 Comments
Map of the West Falls Church Metro development sites (photo courtesy EYA)

(Updated 6/11) A plan to overhaul one of the Metro system’s least-used stations is headed to the Fairfax County Planning Commission next week, but surrounding the new project is a complex network of advocates, issues, and jurisdictional questions that’s built Katamari Damacy-style over the last two years of public engagement.

As the project to transform the area around the West Falls Church Metro station starts to move forward, advocates and opponents alike are already starting to look at the next stage of transportation questions down the road.

The proposed comprehensive plan amendment aims to turn the area near the West Falls Church Metro station into a mixed-use district with office, retail, and residential uses more typical of areas near Metro stations.

With the withdrawal of Virginia Tech taking the filling out of the development sandwich, the two pieces of the plan are the City of Falls Church parcel, with mixed-use developments around a central stretch of park and open space, and the area adjacent to the Metro station.

The first phase of the project is scheduled for a planning commission public hearing on Wednesday (June 16) before going to the Board of Supervisors on July 13, after which the Washington Metropolitan Area Transit Authority’s development team will still need to get specific plans approved.

So far, most of the public discussion about the project has involved transportation.

Evan Goldman, executive vice president of acquisitions for site developer EYA, says an expanded roadway parallel to the crowded Haycock Road should help relieve some of the local traffic, along with a new exit off I-66 running directly to the West Falls Church Metro station.

“There’s no question that what is being built here is 100% better than what is there today,” Goldman said. “This will have dedicated bike lanes on almost all the streets.”

Goldman says the concerns raised so far have mainly focused on the single-family residential neighborhoods near the development, where there are insufficient sidewalks in some places.

“It’s specifically because of the location, surrounded by single-family neighborhoods in an area where there are existing traffic issues,” Goldman said. “The density is sized for the capacity of what the traffic can handle to make sure we’re trying to be respectful of neighbors in terms of height and density.”

Goldman says lower density requirements will also allow more of the buildings to be delivered together, so the project can be brought online all at once.

The reaction from surrounding neighbors to the project has been mixed.

Paul Rothstein, one of the representatives from nearby residential development The Villages on a task force to review the project, has argued that the increased density will pose a hazard to nearby residents, who will feel the ripple effect of traffic from the site on streets not built to handle it.

“Even though I view pedestrian infrastructure remediation as mostly Fairfax County’s responsibility and not [EYA’s],  your development will increase traffic in the surrounding areas and increase the risk to pedestrians,” Rothstein wrote in a letter to the developer.

Rothstein has been pushing for EYA to endorse a McLean Citizens Association resolution on the project, which notes that the traffic issues at the site remain unresolved.

“To quote the father of the injured child, ‘I also hope that the developers, who emphasize building walkable communities, will support the MCA resolution and thus make sure that walkability in existing communities does not deteriorate as a result of new communities,'” Rothstein wrote. “Adoption of the MCA resolution still will permit substantial development at the same time as promoting the safety of your neighbors, including their children.”

Goldman says current plans for the development include dedicated crossings on Haycock and Leesburg Pike, but Rothstein’s concern is for neighborhood children walking to Haycock Elementary along more crowded streets.

Goldman says EYA’s obligations for traffic improvement are primarily at the development site and not the broader region around the station.

Cheryl Sim, another nearby resident, agreed that, by and large, EYA is not responsible for the entire area, but it still has some obligations.

“The County and VDOT have long ignored this area and its needs,” Sim said. “However, EYA fronts for WMATA in this exercise. And, WMATA, based upon its Joint Development Guidelines and Principles from May 2020 place the onus on the developer.” Read More

0 Comments

Morning Notes

County Board Approves PIVOT Grant Program — The Fairfax County Board of Supervisors voted on Tuesday (June 8) to create a new grant program that will use $25 million in federal COVID-19 relief funds to support businesses hit hard by the COVID-19 pandemic. The program will focus on the hotel, food service, retail, and arts and culture industries with applications scheduled to open from June 23 through July 9. [Fairfax County Government]

Armed Robberies Reported in Falls Church — Fairfax County police are investigating a series of armed robberies that have occurred in the 3300 block of Glenmore Drive since Saturday (June 5). In all four cases, a masked man described as white and between 17 to 25 years of age approached victims with a knife and demanded cash or property before running away. [FCPD]

Reckless Driving in Tysons Subject of Capitol Complaint — Architect of the Capitol J. Brett Blanton is under investigation by the agency’s inspector general after a woman “recklessly” drove his work-issued vehicle around Tysons on March 6. A complaint says the vehicle was traveling at a high speed and made an unauthorized stop at Walmart, and the driver “made obscene gestures at the person who reported the incident.” [Roll Call]

Developer Starts Selection Process for Maryland Beltway Project — The development group selected to carry out Maryland’s plan to widen the Capital Beltway at the American Legion Bridge will launch a competitive procurement process on June 16 to identify design and construction contractors. The process will be watched by Virginia, particularly in McLean, as the Commonwealth moves forward with its 495 NEXT project. [Accelerate Maryland Partners]

Reminder: Idylwood Substation Public Hearing Tonight — The State Corporation Commission will hold a public hearing at 7 p.m. today (Thursday) on Dominion Energy’s plans to rebuild a substation in Idylwood. The project has been repeatedly delayed, and the utility company has proposed pushing the timeline for completion back even further to 2026. [SCC]

0 Comments

Morning Notes

Fairfax County Updates COVID-19 Vaccine Dashboard — The Fairfax County Health Department launched an updated version of its vaccine dashboard yesterday (Tuesday) with data on administered doses, how many people have gotten vaccinated, demographic breakdowns, and other information. [FCHD]

Fairfax County Indoor Ski Facility Could Be First of Many — Alpine-X, developers of the planned Fairfax Peak indoor ski and snowboarding facility in Lorton, hopes to expand the concept to more than 20 other locations around the U.S. and Canada. The Fairfax County facility will be the flagship with a luxury hotel, a gravity-powered mountain coaster, zip lines, and food and beverage outlets planned for the area. [Patch]

Bike Lanes Proposed on Chain Bridge Road — The Fairfax County Department of Transportation will hold a virtual meeting at 6:30 p.m. on June 8 to discuss striping changes that would create bicycle lanes on several roads. Among the proposals is the addition of bicycle lanes “where space allows” on Chain Bridge Road from Colonial Lane to Great Falls Street in McLean. [FCDOT]

Falls Church Councilmember Won’t Seek Reelection — Ross Litkenhous, who is serving his first term on the Falls Church City Council, announced on Monday (May 24) that he will not run for a second term when four seats are on the ballot in November. He cited a need to focus on a new company that he recently launched, but he plans to stay involved by applying for the city’s economic development authority or planning commission after his term ends. [Falls Church News-Press]

Del. Simon Addresses Greater Merrifield Business Association — Del. Marcus Simon (D-Falls Church) highlighted the Virginia General Assembly’s work to address the COVID-19 pandemic, an estimated $500 million budget surplus, and bills that dealt with eviction prevention, stormwater management funding, and electric vehicle rebates in a recent presentation to the GMBA. [Sun Gazette]

Falls Church Hires New Public Works Superintendent — “The City of Falls Church welcomes Herb Holmes as the new Superintendent of Public Works. Throughout April, Holmes shadowed the incumbent, Robert Goff, who will retire on July 1 after 40 years of service…Holmes most recently served as the Superintendent of Streets for the City of Alexandria, Virginia.” [City of Falls Church]

0 Comments

Fairfax County wants the public to weigh in on the projects that it plans to submit for funding as part of the Transportation Alternatives initiative, a federal program that gives grants to smaller community projects that expand non-motorized travel or enhance transportation infrastructure.

The Fairfax County Department of Transportation is reviewing four projects that it has proposed submitting for the federal grants: the Vienna/Fairfax-GMU Metro Station bicycle connection, Safe Routes to School projects for Shrevewood and Bush Hill elementary schools, and the Mason Neck Trail.

The virtual meeting will occur at 6 p.m. on Thursday (May 27). County staff will give a presentation at the meeting and provide a Q&A session. Attendees can join online or call 1-844-621-3956 with access code 173 919 2128.

FCDOT spokesperson Robin Geiger said that, once projects are identified, the county often seeks multiple funding sources due to the competitive nature of grants.

The Shrevewood Elementary Safe Routes to Schools project has been the beneficiary of a Transportation Alternatives grant before. The Fairfax County Board of Supervisors accepted $560,000 from the Virginia Department of Transportation in March to support the project, which will add crosswalks, curb ramps, and other improvements outside the school in Falls Church.

The Metro station bicycle project will add dedicated bicycle facilities to Virginia Center Boulevard and Country Creek Road from Nutley Street to Sutton Road, county staff said. It will also include a connection to the I-66 parallel trail being planned with the Transform 66 Outside the Beltway project through protected bike lanes, narrowing an existing median and adding trail connections, according to the county.

The Transportation Alternatives initiative is overseen by the Federal Highway Administration. Projects through the program can assist students, people with disabilities, pedestrians, cyclists and others by adding sidewalks, lighting, and other safety-related infrastructure.

Photo by Michelle Goldchain

0 Comments

Fairfax Connector suspended fare collections last year as a temporary health measure in response to the COVID-19 pandemic, but the public bus system is considering longer-term adjustments to its fare policies with support from a new state grant program.

The Fairfax County Department of Transportation is one of 12 transit agencies in Virginia that have expressed interest in the Department of Rail and Public Transportation’s new Transit Ridership Incentive Program (TRIP), which will fund projects that increase connectivity in highly populated areas or remove barriers for low-income individuals by reducing or eliminating fares.

While fare collection resumed on Jan. 4, county leaders see reducing or subsidizing trip costs as one way to encourage more people to ride the Connector, which is the largest local bus system in Northern Virginia, transporting approximately 30,000 passengers on 91 routes in ordinary times.

“Access to transit is crucial in promoting equity county-wide and for many a barrier is cost,” Fairfax County Board of Supervisors Jeff McKay said. “Our Department of Transportation is committed to looking into how we can provide aid to those experiencing economic hardship.”

Created by the General Assembly during its 2020 session, TRIP was conceived before the novel coronavirus arrived in the U.S., but Virginia Transportation Secretary Shannon Valentine told the Commonwealth Transportation Board during a May 18 workshop that the pandemic illustrated how vital public transportation is for essential workers, DCist reported.

“Fares turned out to be an obstacle. So we are really trying to use this as an opportunity,” Valentine said, according to DCist.

DRPT has split TRIP into two programs: one focused on regional connectivity, which could include everything from integrated fare collection systems to the creation of bus-only lanes on significant routes, and one focused on reducing the impact of fares on low-income users, which could involve eliminating fares, creating zero-fare zones, or providing subsidized or free passes.

Virginia has allocated a total of $129 million to the TRIP initiative through fiscal year 2027, including $88.4 million for the connectivity program and $39.6 million for the fare program, according to a presentation that DRPT delivered to the Commonwealth Transportation Board.

Legislators limited the fare reduction program to 25% of the initiative’s annual funding, but the General Assembly gave the program an additional $10 million in the state’s fiscal year 2022 budget, raising its total to $12.5 million for the upcoming fiscal year, which begins on July 1.

DRPT released a draft policy last week outlining how TRIP will be implemented, including how projects will be evaluated for grant funds. The resolution is open for public input through June 18, and the CTB is scheduled to vote on it on June 23.

The department has also made a draft of the program’s application guidelines available for public comment until July 7. Read More

0 Comments
×