Some attendees at a meeting about a multi-year road project that recently kicked off in the Vienna area said they are worried about traffic impacts.

The Virginia Department of Transportation (VDOT) is currently working on its Transform 66 project, which includes construction near the Vienna/Fairfax-GMU Metro station.

Rich Clifton, the project’s design engineer from FAM Consulting LLC, provided attendees with a construction update at a meeting yesterday (Sept. 4) at the Providence Community Center. Every seat was filled for the presentation at 7 p.m., with dozens of people standing in the back.

Starting today (Sept. 5), the ramp from Saintsbury Drive to eastbound I-66 will be permanently closed.

The ramp will temporarily reopen for buses during the weekday from October 2019 to September 2020 while another road construction project is underway. Clifton strongly urged non-bus drivers to stay off of the ramp.

“The ramp can’t handle the volume of traffic if it was open to the general public,” Clifton. “There are 19 bus routes that go over Vaden.”

Along I-66, the barrier between the collector-distributor (CD) road and eastbound I-66 will be removed and access to I-66 from the CD road and Nutley Street will shift east of Vaden Drive.

On westbound I-66, the lanes will shift, along with the CD road. Clifton said that the exit ramp to Country Creek Drive will remain open.

Starting in October, the bridge at Vaden Drive will close for demolition and construction of a new bridge — a process that will take about a year, Clifton said.

“We’ll try to stay out of Nutley while we work on Vaden bridge,” Clifton said.

While the bridge is closed, drivers will have 2-mile-long detours to follow. A modification of traffic flow at the Nutley Street intersection and Saintsbury Drive will accommodate the detour, Clifton said.

Some attendees at the meeting said that they expect drivers to head west instead of following the detour, possibly clogging up local roads. Clifton said that posted signs about the detours are meant to encourage drivers to take detour routes, but that there is no guarantee that drivers won’t come up with their own directions.

For pedestrians, a shorter detour will allow them to use the bridge at the Vienna/Fairfax-GMU Metro station, which will stay open all day and night. Clifton said that the Washington Metropolitan Area Transit Authority (WMATA) will be able to close off the station, while keeping the gates open for the bridge.

In about six months, work will start on Chain Bridge Road (Route 123) to relocate utilities and to construct bridges, ramps and new box culverts for a future path.

A temporary traffic pattern change will allow for the construction of new ramps:

  • westbound I-66 and northbound Route 123
  • westbound I-66 and southbound Route 123
  • eastbound I-66 and northbound Route 123
  • southbound Route 123 and eastbound I-66

There will also be four new traffic signals in that area.

Once all of that work is finished, construction will start on the Nutley Street and I-66 interchange.

While a diverging diamond design was proposed a few years ago, Clifton said that the interchange will instead have a double roundabout.

That work is slated to finish up in the early part of 2022.

After several questions about traffic for each portion of the project, Clifton told attendees to check out the traffic impacts online.

Maps via VDOT

0 Comments

Community leaders and city officials celebrated the start of an infrastructure project located in the heart of an upcoming mixed-use development in the City of Falls Church.

During a keynote address for the groundbreaking today (Monday) ceremony at George Mason High School, Councilmember David Snyder said that this $15.7 million dollar project will create a safer and more economically successful community around the West Falls Church Metro.

The new improvements, according to the City of Falls Church, include:

  • synchronization of four new traffic signals
  • a high-intensity, pedestrian-activated crosswalk on Haycock Road
  • pedestrian access improvements, such as widening sidewalks
  • bus stop enhancements
  • bicycle access improvements, including near the newly installed Capital Bikeshare stations near the high school campus
  • utility undergrounding and relocation

The money for the project was acquired through the Northern Virginia Department of Transporation.

Infrastructure issues that have been building up over many decades will finally be addressed with this project, Snyder said.

“Twenty years ago this project would not have occurred,” Snyder said. “This is a classic example of the system working.”

The project is still in the “beginning stages,” according to the City of Falls Church website, adding:

The timing of project design and construction will be coordinated with the new High School construction and future Little City Commons development. City staff expects that design, engineering, and environmental work would begin in Fiscal Year 2021, with construction beginning in Fiscal Year 2022.

Lindy Hockenberry, who taught at George Mason High School for 30 years, served for eight years on the Falls Church City Council and spent another 11 years on the city’s Planning Commission before retiring, attended the groundbreaking to show support for the project.

“Its been my life dream to replace George Mason,” she said adding that the school has serious infrastructure problems, like leaky ceilings.

The new high school campus is already under construction and is slated to be completed by early 2021.

Until then, the students will remain in the same building, which will eventually be demolished for a new commercial center, similar to the Mosaic District, Hockenberry said.

“This will be truly multi-modal,” Snyder said, adding that this these updates will allow people easier access to the Metro.

0 Comments

The Virginia Department of Transporation is looking to secure an emergency contract for one of two McLean Roads undergoing long-term repair.

The 1300 block of Kirby Road and Swinks Mill Road by Scott’s Run are still closed due to severe storm damage from July 8 flash flooding. VDOT has said that both roads will stay closed for several months.

In an update yesterday (Thursday), VDOT said that it wants an emergency contract for bridge and road repairs at Kirby Road.

As for Swinks Mill Road, VDOT tweeted today (Friday) that reconstruction of the road’s bridge starts Monday (Aug. 12).

VDOT also provided information on the progress this week for both roads:

Kirby Road at Pimmit Run (VA-695)

  • Structure and bridge crews removed debris from Little Pimmit Run and Pimmit Run.
  • Soil boring cores and test results were completed.
  • Survey work and underground utility location is complete.
  • Design plans are being finalized for an emergency contract.

Swinks Mill Road at Scotts Run (VA-685)

  • Crews removed asphalt and guardrail debris from Scotts Run.
  • Soil boring cores along with results were completed.
  • Survey work and underground utility location have been completed.
  • Bridge design plans are complete.
  • Repairs will be performed by VDOT structure and bridge crews, who will begin work once ordered materials are received.

“Coordination with external agencies is ongoing to ensure efficient repair of damaged utilities, including coordination with federal/state permitting agencies to relocate Little Pimmit Run to its previous stream alignment,” according to the press release.

Kirby and Swinks Mill roads weren’t the only ones damaged — VDOT said that “extensive repairs” were made to 12 McLean-area roads right after the storm.

Photo 3 via VDOT

0 Comments

Construction on improvements to Kirby Road south of Chesterbrook Elementary School is slated to start in September.

The Fairfax County Department of Transportation gave residents an update yesterday (Wednesday) on the sidewalks project spanning from Birch Road to Corliss Court along Kirby Road.

Latesa Turner, an FCDOT engineer, gave a presentation to a small group of people at Chesterbrook Elementary School (1753 Kirby Road) last night shortly after 7 p.m.

The project would add the following new elements to Kirby Road:

  • a 5-6-foot wide concrete sidewalk and ADA-accessible curb ramps
  • concrete curb and gutter
  • drainage inlets and pipes
  • driveway entrances
  • pedestrian crossing and median refuge at Powhatan Street
  • re-alignment of Chesterfield Avenue intersection
  • water main reconstruction and upgrades
  • road pavement and striping

The first phase of the project, which will last between three to four months, will involve closing the westbound lane of Kirby Road to construct the water line relocation, according to the presentation. Drivers can expect traffic maintained in both directions during the lane closure.

Then, the second phase will involve closing the westbound lane of Kirby Road for drainage and utility work, along with work on the curb ramps, driveway entrances, sidewalk and gutter. The second phase is expected to last five to six months, according to the presentation.

The contractor will come out within the next week for clearing and tree removal. Then, construction will start in September. The first phase is slated to be done around December and most of the work will be completed by February. All of the work is slated to be finished by April 2020.

Once finished, Turner said that the Virginia Department of Transportation will maintain the sidewalks.

When asked why it took two years for the project to start construction, Turner said that many steps had to take place after the idea was approved including finalizing the plans, receiving VDOT approval, permitting and bidding for the project after the land acquisition in late 2017.

Despite some grumblings among attendees about waiting for the improvements, many expressed support for the upcoming work.

“I’m really glad you’re doing this,” one attendee told Turner toward the end of the meeting.

Image 4 via Fairfax County

0 Comments

As work continues on the Jones Branch Connector, Scotts Crossing Road, a road between Jones Branch Drive and the off-ramps for I-495 Express Lanes, will close overnight on Thursday (July 25).

The Virginia Department of Transportation said that Scotts Crossing Road will be closed from 10 p.m. on Thursday to 4 a.m. on Friday (July 26). Drivers heading north or south will have several detour options.

More from VDOT:

The ramps from the northbound and southbound I-495 Express Lanes to Scotts Crossing Road will remain open and traffic will still be able to access Route 123 via eastbound Scotts Crossing Road.

Route 123 traffic will still be able to access the northbound I-495 Express Lanes via westbound Scotts Crossing Road.

Currently, the Jones Branch Connector is undergoing construction for a $60 million project that will add two travel lanes and on-street bike lanes in each direction — the two lanes are set to open by the end of the year. Sidewalks are slated to open later this summer.

VDOT expects the project to be completed in spring 2020.

Map via Google Maps

0 Comments

A portion of Church Street in Vienna will be closed for four weeks starting next Monday (May 6) for construction work.

The Town of Vienna hired Ashburn Construction to install a new sidewalk, storm sewer, curb and gutter and driveway aprons on Church Street NE from the intersection of Glyndon Street to 344 Church Street NE. The contractor will also replace the speed hump in front of 342 Church Street NE.

The 300 block of Church Street will be closed from 8 a.m.-4 p.m. on weekdays and only residents who live in that block will be able to access the area, according to the town. Vienna does not have any utility disruptions planned.

During construction, traffic on Church Street will get diverted onto Maple Avenue briefly before returning to Church Street.

Some people commented under Vienna’s Facebook post about the closure that the street needs the improvements, but the work is ill-timed.

“Much needed agreed but wish it was to be done over summer when traffic is a bit less,” one commentator wrote under the post. Another person wrote, “Much needed improvements …. very inconvenient. Sigh.”

Vienna is using the announcement about the road closure to encourage locals to sign up for the town’s new notification system.

First image via Town of Vienna and second via Google Maps

0 Comments

The eastbound lane of Linway Terrace, a two-way street in McLean just north of Chesterbrook, is scheduled to be closed between Bryan Branch Road and Linway Park Drive for much of next week.

The closures will last from Monday, March 25 through Thursday, March 28, according to the Virginia Department of Transportation (VDOT). The closures are planned to last from 8 a.m.-4 p.m. each day for stormwater pipe replacement.

“Linway Terrace will have alternating one-lane traffic via flagging,” VDOT wrote in a press release. “Drivers can expect delays and are advised to use alternate routes.”

Linway Terrance isn’t the only street nearby with roadwork planned soon. Kirby Road, just to the east of Linway Terrace, will likely experience closures as a new sidewalk and other improvements are constructed later this year.

Photo of Linway Terrace via Google Maps. Map of work zone via VDOT.

0 Comments

Several new streets and major improvements to existing ones are in the works for Tysons.

The Fairfax County Board of Supervisors made a small adjustment on Tuesday (March 19) to make developers pay a little more of their share, but the report offers a glimpse at what’s ahead for local roadways.

With no discussion, the Board voted unanimously to approve a 1.9 percent increase in the developer contribution rate to the Road Fund and approval of guidelines for those funds’ usage in Centreville and Tysons.

“One of the principles of the Comprehensive Plan for each of the road fund areas is that development above the baseline level established in the plan may be approved, if developer mitigates the impact of such increased density or intensity by contributing to a fund for the provision of off-site road improvements,” staff said in a report. “All aforementioned road funds function in this manner.”

The staff report also included a list of transportation projects either underway or in planning for Tysons’ streets.

  • Route 123 Improvements: Changes planned for Route 123 in Tysons East in the early stages of being developed as a “superstreet,” which would modify left turn movements to facilitate regional through movement. The project has finished simulations and is currently undergoing initial design.
  • Route 7 Widening and Interchange: A study has been recently completed on a plan to widen Route 7 and implement new improvements at the Route 123 interchange. Stakeholder meetings are planned for this summer.
  • Cleveland Ramp Alternatives: A new ramp is planned to connect the Dulles Toll Road to new sections of the Tysons East grid of streets. Greater access to the Dulles Toll Road is part of several transportations discussions currently ongoing in Tysons.
  • Jones Branch Connector: An alternative access route from eastern to western Tysons passing over I-495. The project is currently in construction with completion planned for this fall.
  • State Street: A new street, named State Street, is being developed to connect Boone Boulevard and Greensboro Drive in Tysons. A study of the project has been completed and options for project implementation are being discussed.
  • Lincoln Street: Another proposed new street to connect Route 123 to Magarity Road, intersecting with Old Meadow Road and other future streets. The core idea for the new street is to move traffic from existing developments northeast of Tysons Galleria to Magarity Road. A feasibility study is ongoing.
  • Center Street: A new street planned within the Tysons urban center. A report is expected sometime this summer.

Many of the new streets listed in the report are centered around the areas northeast of Tysons Galleria and in Tysons East, the points at either end of the Jones Branch Connector and both planned sites for major redevelopment.

0 Comments

A series of closures are planned on and around the Jones Branch Connector this weekend to facilitate more bridge deck work on the bridge.

According to a press release from the Virginia Department of Transportation, the following streets will be closed:

  • The southbound 495 express lanes between the Jones Branch Connector off-ramp and the Jones Branch Connector on-ramp
  • The eastbound Dulles Toll Road ramp to southbound 495 express lanes
  • Eastbound and westbound lanes of the Jones Branch Connector between Jones Branch Drive and the 495 express lanes.

The closures will run from 5 a.m. tomorrow (Saturday) to 4 a.m. on Monday (March 4).

The northbound 495 express lanes ramp will remain an option, but only for drivers turning right towards Route 123 via eastbound Scotts Crossing Drive.

The bridge partially opened in December with final completion planned for fall 2019.

0 Comments

Morning Notes

Tysons Company Tops Fortune List — Tysons-based Hilton is No. 1 on Fortune’s new 100 Best Companies to Work For list. The hotel operator was also joined by local companies Navy Federal (#29, Vienna), Capital One (#39, Tysons), CustomInk (#86, Merrifield) and Mars Inc. (#98, McLean) on the annual list. [Fortune, Twitter]

State of McLean: Under Construction — “McLean is poised to benefit from a raft of infrastructure and revitalization projects, Supervisor John Foust (D-Dranesville) told the Greater McLean Chamber of Commerce Feb. 14 [during] his annual ‘State of McLean’ speech.” [InsideNova]

Falls Church Property Assessments Rise — “Property values are on the rise in Falls Church, according to 2019 assessment data released by the city. Overall residential and commercial property values have increased from January 2018. Commercial property values rose by 4.3 percent and residential real estate values by 2.93 percent over the last year.” [Patch]

0 Comments
×

Subscribe to our mailing list