Work Starts Tonight on GW Parkway in McLean

Drivers can expect lane closures as work begins tonight (Tuesday) on areas of the GW Parkway in McLean.

The National Park Service (NPS) and Federal Highway Administration (FHWA) wants to repair sections of the GW Parkway in McLean and Clara Barton Parkway in D.C.

On the GW Parkway, the work will take place between Chain Bridge Road (Route 123) and I-495. Drivers can expect single-lane closures from 7 p.m. to 5 a.m.

“We’re working this fall so the parkways are ready for winter driving,” Superintendent Charles Cuvelier said in the press release. “Even though this work won’t address the entirety of either road, it’s part of the National Park Service’s long-term plan to maintain and eventually reconstruct both.”

The project plans to level uneven parts of the road, add new pavement markings and replace old asphalt.

“The work will last into late fall with completion depending on the weather in the weeks ahead,” the press release said.

Construction crews are also working to fix the cause of a sizeable sinkhole that opened up on the GW Parkway back in March.

“The FHWA recently finished 50 vertical feet of excavation to remove a 60-year-old brick drainage structure that had failed,” the press release said. “Workers are now completing the installation of a new drain and back-filling the excavated area.”

NPS is also competing for federal grants to fully fund a project that would reconstruct GW Parkway near Route 123.

Map via Google Maps

Recent Stories

An officer who fatally shot a McLean man in 2022 violated Fairfax County Police Department policies, but the shooting itself was within policy and legal bounds, a new report on…

This sponsored column is written by the team at Arrowine & Cheese (4508 Cherry Hill Road in Arlington). Sign up for the email newsletter and receive exclusive discounts and offers. Experience Arrowine’s Tastings & Events. Have…

Inova’s Center for Personalized Health campus in Merrifield (staff photo by Angela Woolsey) Inova Health System appears to be narrowing its vision for the former ExxonMobil headquarters site in Merrifield…

Morning Notes

The “Hoop-La” sculpture in front of Capital One’s Tysons headquarters (staff photo by Angela Woolsey) Police Continue Traffic Enforcement Campaign — “Between April 22 and 28, the Fairfax County Police…

×

Subscribe to our mailing list