FCPS lays out possible timeline for new Dunn Loring Elementary School

Dunn Loring Center (courtesy Fairfax Public Schools)

Planning for a new elementary school in Dunn Loring could begin as soon as the second half of 2022, Fairfax County Public Schools projects in its proposed Capital Improvement Program (CIP) for fiscal years 2023-2024.

As approved by the Fairfax County School Board back in January, the new school will take over the Dunn Loring Administrative Center at 2334 Gallows Road, which started as an elementary school before being repurposed in 1978. The building is now being used for some special education and parent programs.

The project’s estimated $36.7 million budget is already fully funded by money from 2017 and 2019 school bonds that were originally destined for a new school in Oakton High School area.

Funding for the new school was welcomed by parents at Shrevewood Elementary School, which was at 118% capacity in the 2019-2020 school year. The CIP says its capacity dropped to 99% this year after an enrollment decline and minor facility modifications.

However, the boundaries for the Dunn Loring school have yet to be determined beyond it being “intended to relieve overcrowding in the Dunn Loring/Falls Church/Tysons area,” as stated in the CIP.

“School assignments for the repurposed Dunn Loring Elementary School will be determined as part of any boundary study for the school,” FCPS said in a statement. “The boundary study is currently estimated to begin toward the end of construction in 2026.”

The CIP indicates that planning for Dunn Loring Elementary will begin in fiscal year 2023, which starts on July 1. Permitting could start in FY 2024, followed by construction in FY 2025. The project is expected to be complete in FY 2027.

Other Tysons-area projects addressed by the proposed CIP include:

  • Madison High School: a 35,000 square-foot addition, currently under construction and expected to finish by the end of 2022 ($18 million)
  • Louise Archer Elementary School: renovation adding over 50,000 square feet to the building. The voter-approved 2021 school bond included funds for construction, which is expected to start this fiscal year and finish in FY 2024. ($39.9 million)
  • Cooper Middle School: renovation expanding the building by approximately 65,000 square feet. Construction is underway and set to finish in summer 2023. ($54.4 million)
  • Falls Church High School: approximately 126,000 square-foot renovation, in the permitting process with an anticipated construction finish in FY 2026 ($136 million)

FCPS staff will present the proposed CIP to the school board tonight (Thursday). The board will hold a public hearing on Jan. 4 and a work session on Jan. 11, with a final vote scheduled for Feb. 10.

Recent Stories

Fairfax County Courthouse (staff photo by James Jarvis) The Fairfax County Board of Supervisors is considering using kiosks equipped with artificial intelligence to provide select legal information in a variety…

Families with the donated vehicles given to them by NADA and Vehicles for Change (courtesy National Automobile Dealers Association) Commuting will be easier for four families in the D.C. area,…

Just a day after negotiations for a Washington Wizards and Capitals arena in Alexandria officially fell through, George Mason University has announced that it’s no longer planning to build a joint baseball and cricket stadium in Fairfax for the Washington Freedom.

The deal to bring the Washington Capitals and Wizards to Alexandria’s Potomac Yard is officially dead, and the developer says suggestions that an arena could be built in Tysons instead…

×

Subscribe to our mailing list