Repairs are almost done along Leesburg Pike in Tysons as part of the Silver Line’s first phase.
The Dulles Corridor Metrorail Project shared photos of the concrete work on a new ramp along westbound Leesburg Pike, finished sidewalk repairs near the Spring Hill Metro station and finished work on the sidewalk, curb and gutter near Spring Hill Road.
Silver Line Phase 1 includes the four stations (McLean, Tysons Corner, Greensboro and Spring Hill) in Tysons along with the Wiehle-Reston East station.
“Crews will finish repairs along Route 7 and will complete final clean up and punch list items by the end of June according to a project executive,” according to the Dulles Corridor Metrorail Project.
Previously, the Dulles Corridor Metrorail Project shared updates in April on crews placing concrete near Leesburg Pike for a new ADA ramp and excavation work along Old Meadow Road.
Photos courtesy Dulles Corridor Metrorail Project