Playground at Tysons Pimmit Park Expected to Reopen Late March

Updated 3:05 p.m.– Though the project is behind schedule, construction at the Tysons Pimmit Park playground is expected to finish by the end of the month.

Crews at Tysons Pimmit Park (7584 Leesburg Pike) are replacing a picnic shelter, a Fairfax County Park Authority spokesperson said, adding that the area should reopen by late March.

Construction was originally supposed to be finished by Feb. 28, a spokesperson previously told Tysons Reporter.

“There was a need for extra time to accommodate procurement issues and delivery of the equipment,” the Fairfax County Park Authority spokesperson later told Tysons Reporter.

Overall, the project cost $120,000 and is being funded by the 2019 Park Bond, according to county documents.

Recent Stories

The Spring Hill Rec Center now has an active rooftop solar panel array (courtesy Fairfax County Park Authority) The Spring Hill Rec Center in McLean is now being partly powered…

W&OD Trail in Herndon (staff photo by James Jarvis) The Washington & Old Dominion (W&OD) Trail has reached the half-century mark. The Northern Virginia Regional Park Authority (NOVA Parks) is…

Stellina Pizzeria has a launch date for its upcoming Tysons restaurant. The D.C.-based chain will open its largest location yet at Capital One Center (1610 Capital One Drive) in Tysons…

Left to right: Fairfax Alliance for Better Bicycling President Bruce Wright, Hunter Mill District Supervisor Walter Alcorn and Reston Bike Club Vice Chairman Joel Kuester team up to promote the…

×

Subscribe to our mailing list