Traffic will shift to new Gallows Road bridge as soon as tomorrow

The old Gallows Road bridge over I-66 (via Google Maps)

Preparations for the upcoming demolition of the Gallows Road bridge over I-66 in Dunn Loring are about to get underway.

Northbound traffic on Gallows will shift to a new bridge during daytime hours tomorrow (Thursday) with southbound traffic expected to follow suit next week, the Virginia Department of Transportation announced yesterday (Tuesday).

VDOT anticipates starting to demolish the existing bridge around Oct. 23, a process that will take 30 to 40 nights.

Here are more details on the traffic changes from VDOT’s news release:

Pedestrians will continue to use the west side of the current bridge until southbound Gallows Road traffic shifts to the new span. At that time, pedestrian access will be shifted to the east side of the new bridge, with detours using the crosswalks at Cottage Street and Avenir Place/Bellforest Drive.

Following this traffic shift, the current Gallows Road Bridge over I-66 will be demolished to allow for construction of the new southbound bridge span. Demolition of the current bridge is anticipated to begin on or about October 23. Most of the bridge is directly over I-66 or the Dunn Loring Metrorail Station and will need to be demolished during the overnight hours, when multiple lanes can be closed on I-66 and the Metrorail Station and tracks can be closed to safely accommodate this work. Demolition activities will occur during the daytime hours when feasible, to minimize impacts to the nearby communities. Additional information and updates about demolition work and traffic closures will be provided on the project website. All work is weather dependent and schedules may shift if inclement conditions occur.

The replacement of the Gallows Road bridge is part of the Transform 66 Outside the Beltway project, which will extend the I-66 Express Lanes more than 22 miles west from the I-495 interchange in Dunn Loring to Gainesville.

The new bridge will feature improved sightlines, bicycle lanes and wider sidewalks in each direction, and connections to the shared-use path that’s being constructed alongside I-66, according to the project website. It’s being built in two phases, with the southbound side expected to be completed next summer.

The overall Transform 66 project is on track to open the new express lanes in December 2022, VDOT confirmed at a public information meeting last week.

“Drivers should be alert for changing traffic patterns on Gallows Road near I-66 as construction continues through 2022,” VDOT said. “Drivers are reminded to slow down and pay attention to lane markings and roadway signs at all times.”

Photo via Google Maps

Recent Stories

The D.C. area’s first-ever Winter Lantern Festival is coming to Lerner Town Square at Tysons II (courtesy Kaleido Arts & Entertainment Group) Thousands of lanterns will take over Lerner Town…

Fairfax County Public Schools Fairfax County Public Schools could require parental notifications for class materials deemed sexually explicit, but in a deviation from the state, the proposed policy directly addresses…

The Koons Chevy auto dealership at 2000 Chain Bridge Road (staff photo by Angela Woolsey) The developer behind Reston Station and Herndon’s stalled downtown redevelopment has turned its sights to…

A man walks by trash bins next to the curb (via Trinity Nguyen on Unsplash) (Updated at 1:25 p.m.) The service and staffing challenges plaguing trash collectors throughout Fairfax County…

Chris Green is one of the DMV’s finest fitness instructors. A Lululemon and South Block ambassador, he is a coach and mentor to so many. He embodies grace, positivity and motivation in ways that no one else can. If we could all learn a thing or two from him, the world would be a much better place. He does so much for others, and does so with a smile on his face 99% of the time.

He recently ruptured his Achilles and has an incredibly long and tough journey ahead. As if COVID hadn’t impacted fitness professionals enough, throw this in the mix and it’s a double, even triple whammy. CG is no longer able to work and do what he loves for the time being because of this and we’d love your support.

Read More

Submit your own Community Post here for just $99.

The Rhea Baker State Farm Agency is proud to support Shelter House in providing safe places to be during quarantine. Shelter House’s mission is to prevent and end homelessness and domestic violence. Right now they are providing over 200 hotel rooms to those in need in our community. In the past year, across all programs, Shelter House served nearly 500 households comprised of over 1,500 individuals, 60% of which were children.

Of the households that exited shelter, over 70% moved to permanent housing. The Baker Agency has served Vienna and Tysons residents and business owners since 2007 and proudly offers insurance solutions for you home, condo, auto insurance, life insurance and more. We offer complimentary reviews and coach teen drivers to safer, better drivers, and to help keep your auto insurance rates down! We are always happy to talk or text at 703-847-6880.

Submit your own Community Post here for just $99.

×

Subscribe to our mailing list