Fairfax County Public Schools (FCPS) unveiled its proposed fiscal year 2021-25 Capital Improvement Program (CIP) last week.
In November, Fairfax County voters approved a $360 million school bond referendum that includes $2 million in planning funds for a new “Silver Line elementary school,” along with other construction and renovation projects.
For the new Silver Line elementary school, permitting would happen in FY 2022, with permitting in FY 2023 and construction from FY 2024-2026, according to the CIP draft.
The revised budget estimates the Silver Line elementary school will cost $39.5 million.
“Anticipation of the completion of the Silver Line Metro has already spurred higher density residential growth along that corridor which may result in an increase in students within FCPS,” according to the CIP draft.
Along with the Silver Line school, the 10-year CIP forecast expects permitting to start on a new elementary school in Tysons in FY 2027.
Here is information on school renovations in the Tysons area in the proposed CIP:
- Falls Church High School, costing $141.9 million
- Cooper Middle School, costing $52 million
- Dranesville Elementary School, costing $38 million
- Louis Archer Elementary School, costing $29 million
A public hearing will be held on the CIP on Jan. 7 at 6 p.m. at Jackson Middle School (3020 Gallows Road), followed by a school board work session on it on Jan. 13. A vote on the CIP is scheduled to take place on Jan. 23.
Recent Stories

Kilmer Middle School in Tysons has stepped up the presence of its security team today (Friday) in response to an alleged threat of gun violence heard during a fight.
In a message sent to parents at 3:10 p.m. yesterday (Thursday), principal Steven McFarlane said the school had been “made aware of an alleged threat of gun violence that was overheard by students during a fight” that afternoon.